Project
Etihad Rail Network Stage 2 (Package B)
Owner or Developer
Etihad Rail
Main Contractor
China Railway Construction Corporation Limited
Project Duration
13 years
Total Tender value
USD 1.41B
Status
Completed
Address
From Tarif to Al Ain
Cooperation details of the projects
Aggregates,steel

Etihad Rail Network Stage 2 (Package B)

The project’s scope of work involves the construction of the 216-kilometer railway line from Tarif to Al Ain. It also has civil permanent way between Liwa Junction and Al Ain and part of DMA line including one combined freight and one rolling stock facility with a regional office at Al Ain. The 240-kilometer railway is divided into 200 kilometers of mainline in Abu Dhabi and 40 kilometers branch line to Khalifa port.